Community Projects
To keep the community of Inspiration Residential Association, Inc. updated on projects, we have developed a project status tracker. If you do not see an item on the list, let us know by completing the linked form.
Beauregard Monument - Power
We’d like to provide a brief update on the project to install electrical service to the Wisdom Monument sign located on Beauregard.
Work has started involve trenching, conduit installation, and final electrical connections. During this time, you may notice construction crews and equipment near the entrance area.
We will make every effort to minimize disruption and maintain safe access at all times.
The project is expected to be completed within the next two weeks, weather permitting. Once finished, the monument sign will be fully powered, improving visibility and overall community appearance.
We appreciate your patience and cooperation as we complete this improvement. If you have any questions or concerns, please feel free to reach out to management.
Club Inspiration Closure Beginning May 11th
We expect Club Inspiration to be temporarily closed from approximately May 11th through approximately May 20th to allow for the next phase of enhancements, including the installation of a shade structure, completion of the Kool Deck coating, installation of artificial turf, and new restroom flooring. Our goal is to have Club Inspiration reopened just in time for Memorial Day weekend so residents can fully enjoy the holiday. We will continue to provide updates as the schedule is finalized, and we appreciate everyone’s patience during these improvements.
Common Area Tree Inspection
The Association is currently reviewing the common area tree inspection report for all Association-owned locations and coordinating any necessary replacements. In the meantime, our team has already begun removing damaged roots in preparation for new tree installations, ensuring each site is ready for planting once replacements are approved.
Update: Many common area trees have been replaced. Trees will continue to be replaced throughout the first few weeks of May.
Update: Many common area trees have been replaced. Trees will continue to be replaced throughout the first few weeks of May.
Fitness Center - Men's Restroom
Please be advised that one of the urinals in the men’s restroom is currently out of order. We are aware of the issue and are working to have it repaired as soon as possible.
In the meantime, we kindly ask everyone to use the remaining facilities with care and consideration for others.
Thank you for your patience and understanding.
Hope Harbor Repairs- Update
Beginning 04/23/2026, work is expected to begin on the removal of the existing roof structure at Hope Harbor near the playground and entrance gates to the pool facility. Our team and vendors are working diligently to have Hope Harbor ready to open for the season by May 1.
Work at Hope Harbor continues to progress, with the existing roof structure having been removed and shortened. Due to the weather this week, installation of the new roof has been delayed. However, this will not impact the pool opening scheduled for May 1. Unfortunately, a temporary closure during pool season will be necessary to complete the roof installation.
Update: The facility is back open; however, it will be closed again on Monday, May 11th and Tuesday, May 12th to complete additional repairs and enhancements. The seasonal hours for Hope Harbor are; Wednesdays from 7:00 am to 9:00 pm and Friday - Sunday from 7:00 am to 10:00 pm.
Meziere Commons - Electrical Box
The district is working on getting a meter installed at Meziere Commons for an underwater aerator. The box does have some exposed wires, but they are not hot.
Parker Road - Traffic Light
We are happy to confirm that a signal is still very much in the plan. It will be installed in two phases: first, as a temporary solution to keep traffic flowing smoothly, and then as a permanent fixture once the construction project is complete.
Peace Village Common Area on St. Paul
Our team is working with the landscaper to address several shrubs in the common area along St. Paul Road within Peace Village. The landscaper will evaluate the area and determine what can be done with some of the plant material.
Pool Furniture
The Board of Directors has ordered new pool furniture for both Club Inspiration and Hope Harbor. The furniture is expected to arrive the week of May 5th.
Update: The new pool furniture for Hope Harbor has arrived, and we are currently awaiting the remaining furniture for Club Inspiration. The furniture at Hope Harbor will be arranged and reset once the roof repairs have been completed.
Reporting Traffic Concerns in Inspiration
If you observe any of the following, please report it to traffic@co.collin.tx.us:
- Reckless or dangerous driving
- Speeding in residential areas
- Inoperable or abandoned vehicles
- Parking violations
When submitting a report, please include as much information as possible to help county officials review the issue. Helpful details include:
- A photo of the vehicle or incident (if it is safe to take one)
- The license plate number
- A description of the vehicle (make, model, color, etc.)
- The location, date, and time the issue occurred
Right of Row ProjectÂ
Recently, the Board approved repairs to the medians in front of Bush Elementary and Club Inspiration. The first phase of the Right of Way project is underway, with the initial focus on revamping these medians to feature lower landscaping for safer visibility.
Tree replacement has also begun. New Bald Cypress trees were installed near the ponds, and the Board of Directors and Landscape Committee have approved the locations for 96 new trees to be installed in their place, as well as throughout the ROW areas. Tree installation is scheduled to be completed within the first two weeks of May.
These improvements are underway and are expected to be completed this year at no cost to the Association. The Landscape Committee continues to work closely on these enhancement projects, and we will provide additional updates as progress continues.
Sapphire Park- Kangaroo Jumper Closed
Update (04/22/2026): Work at Sapphire Park continues to progress, with the next phase scheduled for next week. This includes the installation of new borders around the play area, removal of the existing mulch, and replacement with new sand. We will continue to provide updates and communicate any temporary park closures as information becomes available
Work at Sapphire Park is scheduled to occur next week, including the removal of the three existing posts. The park will be temporarily closed while this work is completed. We anticipate this will be a one-day project; however, we will keep the community updated if additional time is needed.
Update (05/04/2026): Please be advised that the Kangaroo Jumper at Sapphire Park is temporarily closed while the new fall zone is being installed to improve safety and enhance the play area.
Work is currently underway, with the existing mulch and landscape borders being removed, new borders being installed, and fresh sand being added as part of the upgrade.
We appreciate your patience and understanding during this temporary closure as we work to improve the park for our community. We will provide updates once the project is complete and the Kangaroo Jumper is ready to reopen.
Work is currently underway, with the existing mulch and landscape borders being removed, new borders being installed, and fresh sand being added as part of the upgrade.
We appreciate your patience and understanding during this temporary closure as we work to improve the park for our community. We will provide updates once the project is complete and the Kangaroo Jumper is ready to reopen.
Update (05/06/2026): Work at Sapphire Park continues to progress. The new borders around the play area have been installed, and the new sand has been delivered. We are hopeful that the park will be reopened by tomorrow. We will continue to provide updates and communicate any additional temporary park closures as information becomes available.
Park Signage
The Board continues to review the overall park signage program and explore ways to improve the appearance and consistency of signage throughout the community.
Safety Notice: Sinkhole Near Cutter Crossing Pond
We want to make residents aware of a large sinkhole that has developed near the pond off Cutter Crossing in Harmony. The Association and Collin County WCID No. 3 are aware of the issue and are actively working on a solution. For everyone’s safety, the area has been secured and blocked off.
Please use caution if you are nearby, stay clear of the area, and do not cross the fencing under any circumstances. We appreciate your understanding and cooperation and will continue to share updates as more information becomes available.
Harmony Park Water Fountain
The Harmony Park water fountain is currently turned off due to a leak while our team works to assess the damage and determine the necessary repairs.
Water Wall Enhancement
Update (04/22/2026): Water Wall repairs continue to progress; recent weather has delayed the final waterproofing in the upper pit, and 48 hours of clear weather will be needed for proper curing before startup. We are working closely with the vendor and hope to have the project completed no later than the second week of May.
Beginning later this week, the Association will begin major repairs to the Water Wall. The existing letters will be temporarily removed, and next week the vendor will begin removing the current black stone behind the letters. It will be replaced with a similar-colored stacked stone to improve the appearance and durability of the feature. The project is expected to take approximately four weeks and completed in early May.
Update (04/29/2026): Water Wall repairs continue to progress; recent weather has delayed the final waterproofing in the upper pit, and 48 hours of clear weather will be needed for proper curing before startup. We are working closely with the vendor and hope to have the project completed no later than the second week of May.
Update (05/06/2026): Water Wall repairs continue to progress. We expect the letters to be reinstalled by the end of this week or early next week, with the Water Wall fully operational by the end of next week. We are working closely with the vendor to complete the project and will continue to provide updates as progress continues.
Wisdom Park Enhancements
Update(04/22/2026): Work at Wisdom Park continues to progress, with the concrete posts for the new shade structure now installed and currently curing. Once the curing period is complete, the poles and shade structure are expected to be installed by the second week of May. We will continue to provide updates and communicate any temporary park closures as information becomes available.
Work at Wisdom Park is scheduled to take place this week (04/22/2026), including the installation of a new shade structure over the playground area. We will continue to provide updates and communicate any temporary park closures as information becomes available
Update (04/29/2026): Work at Wisdom Park continues to progress, with the concrete posts for the new shade structure now installed and currently curing. Once the curing period is complete, the poles and shade structure are expected to be installed by the second week of May. We will continue to provide updates and communicate any temporary park closures as information becomes available.
Update (05/06/2026): Work at Wisdom Park continues to progress; the posts and shade structure are expected to be installed by the end of next week. We will continue to provide updates and communicate any temporary park closures as information becomes available.
Prior Completed Projects
vvvgvf